Jacksonville, Florida, November 27, 2025
JEA has approved a $1.57 billion natural gas-fired power plant in North Jacksonville to address the growing energy demands of Northeast Florida. Set to be operational by 2030 or 2031, the new facility will replace the aging Northside Generation Station Unit 3 and is designed to generate up to 675 megawatts, enough to power around 300,000 homes. Although it promises enhanced reliability, the investment may lead to increased electricity rates for customers.
JEA Approves $1.57 Billion Power Plant to Meet Jacksonville’s Energy Demands
New natural gas-fired facility to enhance reliability and support growth in Northeast Florida
Jacksonville, Florida – In a pivotal move towards strengthening Northeast Florida’s energy infrastructure, JEA has approved the construction of a $1.57 billion natural gas-fired power plant. This state-of-the-art facility will be situated on the former St. Johns River Power Park site in North Jacksonville, with an expected operational date set for 2030 or 2031. The initiative is aimed at addressing the rising electricity demand in the region, as the local population continues to grow and consumption rates escalate.
The JEA Board of Directors made a unanimous decision on August 26, 2025, paving the way for CEO and Managing Director Vickie Cavey to finalize agreements with GE Vernova. The new combined cycle plant is designed to generate up to 675 megawatts, enough power for approximately 300,000 homes in Northeast Florida. This significant infrastructure investment reflects JEA’s commitment to ensuring reliability and sustainability in energy production, essential for supporting the region’s ongoing economic development.
Replacing and Enhancing Existing Infrastructure
Currently, the Northside Generation Station Unit 3, operating for over 48 years, is scheduled for retirement by 2031. Its age, along with the rising costs of maintenance and anticipated environmental regulation challenges, underscores the need for a more efficient power generation solution. The new combined cycle power plant will replace the retiring unit and significantly enhance power generation capabilities. By utilizing both gas and steam turbines, this plant can produce up to 50 percent more electricity from the same fuel, promoting efficiency while maintaining environmental accountability.
Understanding the Impact on Rates
While the new power plant promises enhanced production capacity, it also comes with implications for JEA’s customers. The robust investment required for the construction and operation of the plant is expected to lead to an increase in electricity rates. JEA has been proactive in managing fuel expenses and reducing carbon emissions through initiatives like the closure of Plant Scherer’s coal-fired Unit 4 in Georgia, positioning itself toward a more sustainable future. However, the scale of investment in the new facility will necessitate careful adjustments to ensure continued service reliability without compromising affordability.
Supporting Jacksonville’s Growth and Future
This power plant project is a testament to Jacksonville’s entrepreneurial spirit and resilience. As local businesses and the wider community anticipate growth, JEA’s developments will play a significant role in ensuring that energy demands are met effectively. By fostering a reliable and sustainable energy framework, JEA is not only addressing current needs but also laying the groundwork for future economic prosperities in Jacksonville and the surrounding areas.
Community and Economic Development
Investments in energy infrastructure like the new natural gas power plant can foster broader economic growth by attracting businesses, creating jobs, and improving the overall quality of life for residents. As Jacksonville continues to evolve as a key player in Florida’s economy, stable energy resources will be essential in supporting this trajectory. Local entrepreneurs and industries can thrive in an environment where energy reliability is prioritized, bolstering Jacksonville’s position in the competitive landscape.
Conclusion
The recent approval by JEA reflects a strategic approach to meet Jacksonville’s energy needs amid growing demand. As the region’s population expands, so too does its energy consumption, necessitating robust infrastructure improvements. While there will be challenges, particularly concerning electricity rates, the benefits of a new combined cycle power plant will extend far beyond mere power generation – they are integral to supporting the future of Jacksonville’s economy. Community members are encouraged to stay engaged and support local initiatives that contribute to Jacksonville’s economic vitality.
Frequently Asked Questions (FAQ)
What is the purpose of the new natural gas-fired power plant?
The new plant aims to enhance system reliability and meet the growing electricity demand in Northeast Florida by generating up to 675 megawatts of power, sufficient to supply approximately 300,000 homes.
Where will the new power plant be located?
The facility is planned for the former St. Johns River Power Park site in North Jacksonville.
When is the new power plant expected to be operational?
The plant is expected to be operational by 2030 or 2031.
Why is JEA retiring Northside Generation Station Unit 3?
Unit 3 is scheduled for retirement by 2031 due to its age, costly repairs, and potential challenges with environmental regulations.
Will this project lead to an increase in electricity rates for customers?
Yes, the substantial investment in the new power plant is expected to result in a rate increase for JEA customers to ensure the continued reliability and sustainability of services.
Key Features of the New Power Plant Project
| Feature | Description |
|---|---|
| Location | Former St. Johns River Power Park site in North Jacksonville |
| Capacity | Up to 675 megawatts, sufficient to power approximately 300,000 homes |
| Operational Timeline | Expected to be operational by 2030 or 2031 |
| Reason for Construction | To replace and increase electricity production from the retiring Northside Generation Station Unit 3 |
| Impact on Rates | Expected to lead to a rate increase for JEA customers to support the investment |
Deeper Dive: News & Info About This Topic
HERE Resources
AARP Petitions Against Jacksonville’s $1.57 Billion Gas Plant
Jacksonville Named New Host City for School Basketball Championships
Local Community Takes Stand Against Industrial Plant Expansion
Ukraine Celebrates Independence Day with Unwavering Resilience
Ring Power Corp. Receives Permit for New Jacksonville Facility
Historic Flooding Hits Southeastern Wisconsin Following Weekend Rainstorm
Severe Weather Causes Power Outages for Jacksonville Residents
JEA Approves Historic $2.37 Billion Budget for Jacksonville
Russia Issues Warning on US Role in Iran-Israel Conflict
Lightning Strike Causes Power Outages and Water Disruptions in Jacksonville
Author: STAFF HERE JACKSONVILLE WRITER
The JACKSONVILLE STAFF WRITER represents the experienced team at HEREJacksonville.com, your go-to source for actionable local news and information in Jacksonville, Duval County, and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as the Jacksonville Jazz Festival, Riverside Arts Market, and World of Nations Celebration. Our coverage extends to key organizations like the Jacksonville Chamber of Commerce and JAXUSA Partnership, plus leading businesses in logistics, healthcare, and entertainment that power the local economy such as CSX Corporation, Baptist Health, and VyStar Credit Union. As part of the broader HERE network, including HEREOrlando.com, HEREStPetersburg.com, HERETallahassee.com, and HERETampa.com, we provide comprehensive, credible insights into Florida's dynamic landscape.